Bump Testing GX-2012s and Gas Tracers 188
16. After air is applied, and if the ppm sensor passed the zero adjustment,
calibration gas from the GAS 2 cylinder will be applied to the ppm sensor. The
GAS 2 indicator on the program screen will come on and calibration gas will be
applied to the ppm sensor for the duration specified in the Gas Exposure Time
parameter in the Configuration Window.
Figure 148: GAS 2 PPM Gas Flowing
The PC Controller program will analyze the results. If the bump test on the
ppm sensor fails and Force Calibration is selected, a calibration will
automatically begin on the ppm sensor and GAS 2 calibration gas will continue
to flow.